On the Ground: Japan's Nuclear Restarts – Macquarie Sector Report

Macquarie · September 28, 2026

A site visit to TEPCO's Kashiwazaki-Kariwa Unit 6 confirms Japan's engineering capability to restart idled reactors, though Chubu Electric's withdrawal of Hamaoka Units 3 and 4 removes 2.24GW from the late-2020s pipeline. Japan's around-2030 identifiable restart queue has shrunk to ~3.4GW, highlighting that restarts must be evaluated plant-by-plant rather than assumed via broad policy timelines.

Read the remaining 4 pages

Finvaulta summarizes Macquarie's analysis. Attribute opinions, forecasts, time-sensitive values, and chronology to the issuer and report date; do not treat this page as an independent verification or a current market-data source.

Key Takeaways

  • 1.TEPCO's Kashiwazaki-Kariwa Unit 6 (1.36GW) returned to commercial operation in April 2026, marking TEPCO's first operating unit since Fukushima and proving large idled reactors can return.
  • 2.Chubu Electric withdrew restart applications for Hamaoka Units 3 and 4 (2.24GW) due to flawed seismic assessment methodology, removing them from the late-2020s queue into the 2030s.
  • 3.Japan remains committed to expanding nuclear generation to roughly 20% by 2040 (up from 9% today), but the identifiable queue around 2030 has narrowed to approximately 3.4GW across Tomari 3, Tokai Daini, and KK7.

Table of Contents

  • Key Points
  • A rare look at a crucial restart
  • Hamaoka is bad news, not a policy reversal
  • Reminder of the export opportunities for Japan
  • Top sector picks unchanged; key catalysts
  • Energy Transition & Critical Minerals Asia
  • A rare look at a restart
  • The scandal elsewhere
  • Global plans still need to become orders
  • Four visits across the Japanese value chain
  • Global peers valuations for nuclear basket

Report data

Figure 6 - Japan restart outlook: what has moved

MetricEstimateContext
Kashiwazaki-Kariwa Unit 6 capacity1.36 GWReactor capacity of KK6, which returned to commercial operation on 16 April 2026.
Kashiwazaki-Kariwa total site capacity across 7 units8.2 GWTotal installed capacity of the world's largest nuclear power station.
Hamaoka Units 3 and 4 combined capacity removed from queue2.24 GWCapacity removed from the late-2020s restart queue following application withdrawal by Chubu Electric.
Japan target nuclear power generation share by 204020%National target for nuclear power generation share, up from 9% today.
Japan current nuclear power generation share9%Current share of nuclear in Japan's total power generation.
Source: TEPCO; Chubu Electric / METI / IAEA; METI. This is a dated model snapshot, not a live forecast.