Bernstein

Report published August 28, 2026

Bernstein European Utilities Daily: Data Center Power Demand, PPA Regulations & Clean Energy (August 28, 2026)

Source and citation context

Issuer
Bernstein
Report date
August 28, 2026
Analysis as of
August 27, 2026

Authors / editors: Jorge Alonso Suils, Bartlomiej Kubicki, Thibault Dujardin, Rory Graham-Watson, Ken-Ree Choong

Finvaulta summarizes Bernstein's analysis. Attribute opinions, forecasts, time-sensitive values, and chronology to the issuer and report date; do not treat this page as an independent verification or a current market-data source.

Daily UpdateCommoditiesEquitiesEnergyUtilities

Bernstein's European Utilities Daily recaps daily headlines including Voltalia's $35bn Brazil data center approval, Spain's 80% hourly renewable mandate for data centers, and Fortum's Swedish nuclear state aid application. It also provides current valuation multiples and ratings for European utilities.

Key Takeaways

  • 1.Spain's government published draft legislation requiring future data center operators to guarantee on an hourly basis that at least 80% of their electricity is renewable via self-consumption or 10-year PPAs.
  • 2.Voltalia won authorization for a $35.24bn (BRL 181.7bn) mega data center project at the Pecem port complex in Ceara, Brazil, which includes wind/solar capacity expansion and tax exemptions.
  • 3.Fortum's NuCore Energi submitted a state aid application to the Swedish government to negotiate financing frameworks (state loans, 2-way CfD, risk-sharing) for a potential 1.2-3.4GW nuclear plant at Oskarshamn.

Table of Contents

  • FEATURED RECENT RESEARCH
  • HEADLINES
  • FRANCE
  • IBERIA
  • NORDICS
  • UK
  • PAN & OTHER EUROPE
  • RESEARCH & MODEL LIBRARY
  • MARKETING DECKS
  • REGULATED NETWORKS PRIMER SERIES
  • PM CHEAT SHEETS
  • BLACKBOOKS
  • FUNDAMENTAL NOTES/RECENT RESEARCH
  • COMMENTS/QUICK TAKES
  • BERNSTEIN TICKER TABLE
  • DISCLOSURE APPENDIX

Report data

BERNSTEIN TICKER TABLE — as of August 27, 2026.

MetricEstimateContext
Voltalia Brazil data center planned investment35.24 USD BillionInvestment in the planned data center at the Pecem port complex in Ceara state (BRL 181.7bn).
Spain annual average free ETS allowances38.1 Million allowancesSpain allocated free GHG allowances to 664 installations, valued at ~€3bn/year.
NuCore proposed Swedish nuclear plant capacity1.2-3.4 GWPotential newbuild nuclear plant at Oskarshamn.
Nordic power demand expected growth from data centres40.0%Expected rise in Nordic power demand spurring battery storage profitability.
Lost EU renewable output due to grid and storage constraints10.0 TWhCurtailments flagged by Ursula von der Leyen as unacceptable.
Source: Reuters; Platts; Montel. This is a dated model snapshot, not a live forecast.

Document Preview

Page 1 of 5
Page 1 of Bernstein European Utilities Daily: Data Center Power Demand, PPA Regulations & Clean Energy (August 28, 2026)
Subscribe for full access

Access the Full Report

Get unlimited access to institutional research reports. Create an account to get started.

Authors / Editors

Jorge Alonso SuilsBartlomiej KubickiThibault DujardinRory Graham-WatsonKen-Ree Choong

Reported Data Context

  • Voltalia Brazil data center planned investment: 35.24 USD Billion · Source: Reuters
  • Spain annual average free ETS allowances: 38.1 Million allowances (2026-2030) · Source: Platts
  • NuCore proposed Swedish nuclear plant capacity: 1.2-3.4 GW · Source: Platts
  • Nordic power demand expected growth from data centres: 40.0 % · Source: Montel
  • Lost EU renewable output due to grid and storage constraints: 10.0 TWh · Source: Platts

Securities

IberdrolaFortumEnelEngieSolariaUnited UtilitiesSevern TrentCentrica

Themes

Data Center Power Demand and Renewable PPA RequirementsEuropean Nuclear & Clean Energy ExpansionEU ETS and Carbon Pricing Policy

Regions

EuropeUKLatin AmericaFranceSpainSweden