Report published September 25, 2026
US Power & Utilities: Watt's On Tap Next Week – Bank of America Weekly Preview
Bank of America · September 25, 2026
BofA previews the week of September 28 – October 2, 2026, highlighting an expected FERC order on PJM's Reliability Backstop Procurement, Michigan PSC's review of DTE's Google data-center contract, and Oklo's facility tour. The note also tracks key active utility regulatory dockets nationwide.
Read the remaining 4 pages
Finvaulta summarizes Bank of America's analysis. Attribute opinions, forecasts, time-sensitive values, and chronology to the issuer and report date; do not treat this page as an independent verification or a current market-data source.
Key Takeaways
- 1.FERC's anticipated PJM Reliability Backstop Procurement (RBP) order will shape eligibility, compensation, and opt-out rules for retiring coal, gas, and nuclear generators to access backstop capacity revenue.
- 2.The Michigan PSC's October 2 meeting is slated to address DTE Electric's special contract with Google for data-center load, setting an early regulatory template for large-load hyperscaler contracts.
- 3.Oklo's analyst tour of the Groves Isotope Test Reactor in Texas tests execution on its isotope production business and offers insight into licensing timelines and advanced nuclear deployment economics.
Table of Contents
- Key takeaways
- PJM FERC order on RBP (anticipated)
- MI PSC: DTE/Google contract expected on agenda
- Oklo analyst meeting and facility tour
- Weekly Utilities Roundtable – Monday 9/28 at 4:30pm ET
- The Calendar
- Exhibit 1: Catalyst calendar for next week
- Our Latest Research
- Exhibit 2: Active Dockets Universe
- Dockets to Watch
Report data
Exhibit 1: Catalyst calendar for next week
| Metric | Estimate | Context |
|---|---|---|
| RBP submission window duration | 2026-09-30 to 2026-10-21 calendar window | Submission window for generators to document qualifying capacity or opt out under PJM's Reliability Backstop Procurement mechanism. |
| Missouri-American Water requested rate increase | 191.9 USD millions | Missouri-American Water general rate case requested increase across dockets WR-2026-0304 / SR-2026-0305. |
| Valara data-center power plant capacity | 450 MW | Valara data-center-associated gas-fired power plant in South Carolina PSC docket 2026-158-E. |
Access the full report
And others from the leading tier 1 banks.
Free account: read previews and a daily allowance of full reports. Pro removes the daily limit.
Authors / Editors
Related Reports
European Fund Manager Survey: European Cheer, Global Hesitation
October 13, 2026
Global Fund Manager Survey: The Sixth Sense
October 13, 2026
ABS Weekly: Personal Loan ABS
October 9, 2026
What to Do at These Rate Levels: Cautiously Overweight Basis & Fast Paying Discounts
October 9, 2026
6% Is the New 5%: Higher Treasury Yields Weigh on Issuance and Refinance Success
October 9, 2026